|
Kemira Colliery
(Albert Mine, Osborne Wallsend Colliery, Mt. Keira Colliery)
1857 - 1991
The Albert Coal Mine, the
first mine in the Illawarra, produced coal from both the Wongawilli and
Balgownie coal seams was abandoned in 1856. A new mine was opened just a short
distance away, higher on the slopes of Mt. Keira, in the Bulli seam in 1857.
This was to become one of the oldest producing mines in Australia.
Owned by Henry Osborne, the
Osborne Wallsend Colliery was opened in April, 1857, working the Bulli seam for
the first time on record.
On April 16th, 1857, 3.5 tons
of coal was delivered to the wharf at Belmore Basin by bullock team, for trial
in the S.S. Illawarra , which sailed to Sydney the following day.
Initial workings were by the
Welsh bord method, drilled by hand and blasted. Forked into approximately 1 ton
capacity wooden skips and hauled from the face by horse.
Progress included the
installation of a Main and Tail Rope Haulage to the surface, a weighbridge and
screens at the tunnel mouth and a self acting skip incline to the foot where
bullocks and horses hauled the skips to the harbour.
Eventually a tramway was
constructed to Belmore Basin, opening in May, 1861.
Several coke ovens were
erected near Wollongong in 1876 utilising slack coal.
The first steam locomotives
(Keira No.1 and Keira No.2) to work on the South Coast replaced the horse teams
hauling coal to the wharf in 1878 only ceasing to run in November, 1954 when the
line was closed.
On the 8th November, 1899, the
colliery was purchased by Mr. Ebenezer Vickery and Sons.
|

Mt. Keira Colliery
around 1905
|
During the early part of the
1900s the daily average output was some 600 to 700 tons, however in the 1930s
coal contracts were difficult to come by and production days slumped to a
minimum of 23 days worked in 1932.
Mt. Pleasant Colliery, on the
northern side of Osborne Wallsend Colliery, was acquired by E. Vickery and Sons
in 1935, changing its name to Keira Pleasant Tunnels.
Production had fallen to 450
tons per day in 1936 and on 26th January, 1937, The BHP Company Ltd. purchased
the Osborne Wallsend Colliery to supply coal to its' rapidly expanding
steelworks at Port Kembla.
A power house, previously
built at Mt. Pleasant Colliery, was refurbished and commenced supplying power to
the Osborne Wallsend Colliery in November, 1938.
A "Samson Coal
Cutter" was introduced as the first step in mechanisation, commencing to
cut coal on 25th November, 1938, in the 5 Left Machine District, followed by
another coal cutter, a scraper loader and a 9X Sullivan Track Cutter placed in
No.3 Right District in July, 1939.
On the 4th March, 1940, power
generated at the steelworks was connected to the mine.
Mechanisation continued with
the introduction in 1940 of Jeffrey L400 Loaders (triggering a 4 week strike),
and an Atlas battery powered electric loco.
In 1942, transportation of the
men in and out of the pit was by rail track using the first diesel powered loco
to operate underground in Australia.
In 1946 operations were
commenced in the Wongawilli seam, using cutters, loaders, an Atlas loco and 6
ton skips. After advancing some 125 metres from the portal, roof conditions
deteriorated and water accumulation became a problem.
On the 6th September, 1950,
operations ceased in the Wongawilli seam, conditions having become untenable.
Equipment was transferred to
the Mt. Pleasant site, producing coal from the 16th December,1950 to the 30th
September, 1955, when the available coal was exhausted. Operations at the Mt.
Pleasant Colliery site then ceased.
Incorporated into the
modernisation programme was a tunnel, 4.8 kms in length, driven from the
escarpment and intersecting with the workings to give direct access to the
companies private railway line to the steelworks.
Called the Kemira Tunnel, it
was commenced on 1st October, 1948 and holed into the colliery workings on the
30th August, 1954. On the 8th November, 1954, this tunnel became the haulage
road for the mines output and also allowed a rearrangement of the collieries
ventilation system.
On the 7th February, 1955, the
colliery changed its name from Osborne Wallsend (known locally as Mt. Keira) to
Kemira Colliery. (a combination of Kembla & Keira).
Five Joy 1CM3 Continuous
Miners were introduced over a period commencing in December, 1955, to January,
1960, operating in both development and pillar extraction panels.
|
189
employees (60% of the workforce) were
handed their retrenchment notices
on 29th October, 1982. This was followed
by a protest in the form of an
underground "sit-in" by 30 employees
lasting 16 days
|
Fletcher Roof Bolters were
introduced in January and Joy 10SC Shuttle Cars in September, 1958.
1960 saw the introduction of
Joy 11BU and 14BU loaders and an Anderson Boyes Trackless Cutter.
The mid 1960s saw the
introduction of the first successful application of mechanised longwall mining
in New South Wales with seven longwalls of varying length being extracted from
the 7 Right District, with completion of LW #8 (#7 was not extracted due to
geological conditions) in February, 1972.
In order to transport coal
from the company's mines to the west, down the 305 m escarpment, an underground
Belt Drift was constructed from O'Brien's Gap to the foot of the escarpment.
Housing a 1,707 m conveyor belt, the Drift commenced operations on 9th May,
1966.
A trial of "shortwall"
during 1971 failed to reach its potential and was consequently withdrawn.
Due to a shortage of #3 seam
(Wongawilli) coal required for the steelworks at Port Kembla, development in the
Wongawilli seam was trialled with production commencing in W1 panel on 14th
March, 1977.
Between August 1981 and
September 1982, a 1,200 ton storage bin was constructed by raising a staple
shaft between the Kemira Tunnel and the Wongawilli seam workings. The bin was
commissioned on the 9th April, 1984.
Due to the deterioration of
the market for steel, reductions in coal requirements followed with the
inevitable reduction in labour requirements resulting in 189 employees (60% of
the workforce) were handed their retrenchment notices on 29th October, 1982. A
protest in the form of an underground "sit-in" by 30 employees for
some 16 days was undertaken, however to no avail and the retrenchment notices
remained.
Bord and pillar development of
the Wongawilli seam continued using Jeffrey Model 120H Heliminers.
Longwall mining was
reintroduced to Kemira in 1988 but was unable to prevent the final closure of
the colliery on Friday, September 27th, 1991.
Spires, Robert, 1984.
History of Kemira Colliery, 1857 - 1984.
|