|
(Rev 0)
Huntley Colliery
1946 1989
Located
below the escarpment at Avondale, west of Dapto, Huntley Colliery was first
opened as a small hand worked mine from the outcrop in the Tongarra seam of the
Illawarra Coal Measures by the Waugh Bros. (Phil, Frank and William) in 1946.
Originally
named Huntly, as the family had an affiliation with Huntly in New Zealand, it
was purchased by the Joint Coal Board on 27th July, 1951 and by the
Electricity Commission of NSW on 15th June, 1955 to service the
requirements of the newly constructed Tallawarra Power Station on the western
shores of Lake Illawarra.
Mr.
M.(Mick) N. Nielsen was appointed the first Mine Manager in October 1951.
The power
station came on stream with No. 1 Unit going on full load on the 6th
September 1954. Other units
progressively came on stream up to 1961 when the
commissioning of No. 6 Unit gave the station a total capacity of 320 MW.
Coal was transported to the power station some 7.5 km by road.
The mine
continued to expand and with the increasing world demand for coking coal, both
domestic (Australian Iron and Steel - AI&S) and export
(Japanese) markets were sourced.
|
In December 1985 it was reported in the Illawarra Mercury
that an unusually high rate of a rare form of cancer had been diagnosed
amongst the miners at Huntley Colliery.
|
By 1966
the mines production peaked at 1,037,829 tons (weighed) -
the first to exceed a million tons in
a year in Australia - and
remained near this level for 14 years with a maximum of 488 employees.
In
January, 1967 a dense media washery was commissioned to produce a high fluidity
coking coal.
As rail
was not available, coking coal was transported to the BHP Port Kembla steel
works or coal loader by road, approximately 20 kms from the washery site.
Additional
leases were sought and granted, by an extension
southerly to Macquarie Pass.
In June
1982, a decline in the world demand for high quality coking coal and a downturn
in power generation requirements led to a sequence of rationalisation to cope
with the reduced demand. This coincided with the conclusion of Huntleys
contract with AI&S.
On
17/01/1983, the adjacent Avondale Colliery closed and was purchased by Huntley,
incorporating it into their leasehold.
In 1983
Huntley was limited to a reduced capacity of 450,000 tons/annum to supply
Tallawarra Power Station (itself operating out of priority) and/or for local or
export consumption. A system of natural attrition was introduced reducing the
workforce by 91 to 349.
Modifications
to the coal beneficiation system were added in 1983/84 by way of a dry screening
plant prior to the washery, virtually eliminating the production of tailings.
In
December 1985 it was reported in the Illawarra Mercury that an unusually high
rate of a rare form of cancer had been diagnosed amongst the miners at Huntley
Colliery. Seven men were currently unable to work, diagnosed with lymphoma (out
of a workforce of 400) and two others had died from lymphoma during the 1960s.
A major
investigation was approved in February 1986, funded by
the Federal Government and headed by Dr. Steve Corbett
of the South Coast Workers Medical Centre (who raised the alarm initially) and
Dr. Barry ONeill, a Wollongong Hospital haematologist. A comprehensive
workplace environment survey was undertaken at the colliery by a combined group
of selected persons becoming known as the Lymphoma Committee.
As the
cause of non-Hodgekins lymphoma was unknown, tests
were conducted relating to oil mist, airborne dust, radon levels, electrostatic
and electromagnetic fields, the presence of particular substances in the
atmosphere and any unusual levels of certain
chemicals, herbicides, pesticides and PCBs.
Nothing
was identified as being especially different and the investigation concluded the
incident was simply a statistical anomaly. However the
investigation prompted the
commencement of a cancer register to assist in tracking down the
incidence of all cancers among Southern Districts coal miners.
Meanwhile, in 1987, further manning
reductions were found to be necessary and a Voluntary Retrenchment
Scheme was introduced, reducing the workforce by a further 120 to 229, with coal
delivered to Tallawarra being restricted to a maximum of 280,000 tonnes/annum.
In 1989,
discussions surrounding the proposed plans to expand Tallawarra Power Station by
the addition of 2 x 660 MW generators (C station) were
revived and lifted expectations at the mine and within the local
community. However, the decision
was made not to proceed. This subsequently led
to the demise and closure of Huntley Colliery.
On 14th
June 1989 the Chairman of the Electricity Commission of NSW announced the
closure of Tallawarra Power Station and Huntley Colliery. On 17th
July 1989 the total
workforce of Huntley was retrenched.
The closure was
completed on the 12th, 13th and
14th of August 1989, when an auction was
held on site of all the collierys remaining equipment including;
-
5 x 5012N Marietta
continuous miners,
-
1 x AM50 Alpine continuous miners,
-
15 x HE 10-50 shuttle cars,
-
4 x 24 seat Gemco Battery man cars,
-
2 x 25 tonne Gemco Battery locomotives,
-
1 x Baldwin diesel locomotive,
-
2 x Mine fans (162 & 96),
-
10 x auxiliary underground fans,
-
15 drive heads and 21 km of conveyor belt,
-
30 km of Victaulic pipe,
-
1 x 400 t/hr dense media washing plant,
-
6 x motor vehicles,
etc etc.
On the 6th
September 1989, after allegations that toxic material
had being dumped underground in the 1960s, a
committee was set up under Mr. R. Burbidge QC and a
further inquiry related to the lymphoma concerns was
instigated.
After
taking evidence in both Sydney and Wollongong Courts, adjourning for several
weeks to permit additional testing, the final hearing was on 16th
March 1990.
Mr.
Burbidge QC, in his executive summary of the inquiry report stated in part;
The Committee
concludes that there has been established no identifiable circumstance peculiar
to Huntley Colliery likely to increase the risk of persons contracting cancer.
Dated 9th April, 1990.
During
the majority of its lifetime Huntley Colliery worked both the Wongawilli and
Tongarra seams simultaneously. A bord and pillar mine, utilising pillar
extraction, the underground workings were serviced by rail and rubber tyred
equipment. Rubber tyred self propelled vehicles loaded with supplies were
piggybacked by flattops from the surface to within approximately 1 kilometre
of the working faces. In the main the Tongarra seam was serviced only by rubber
tyred vehicles.
Access was by adits
directly into the outcrop, a 1:17 drift from the Tongarra seam up to the
Wongawilli seam with all coal exiting the mine via the Tongarra seam after
passing though a 1000 tonne inter-seam bin from the
Wongawilli seam. A Bradford Breaker was installed at seam level prior to a
crushing plant from where it descended by overland conveyor to the coal
preparation plant at the base of the foothills. Coking and fuel coal products
were transported by road to either Pt. Kembla or Tallawarra Power
Station, the rejects being transported by conveyor and then truck to one
of several stockpiling areas or utilised in the making of tailings dams on site.
Ventilation
of the Wongawilli seam was by means of a 280 metre upcast shaft and a 162 Hi
Flow centrifugal fan drawing 150 m3/sec and serving 6 continuous
miner panels.
The Tongarra seam was ventilated independently by a 96 Richardson axial
flow fan situated at the seam outcrop, drawing some 70 m3/sec and
serving 2 continuous miner panels.
Typical roadway
support during the mid 1980s was:-
-
Wongawilli seam 4.7 m wide with 4.5 m
purlins or straps at 1.5 m centres. 2.7 m x 25 mm chemically anchored roof
bolts (2 per strap with a centre bolt when required). Continuous rib strapping
using 1 m bolts at 1.5 m centres.
-
Tongarra seam 4.3 m wide with 4 hole x 4
m W straps at 1 m centres. 2.1 x 25 mm chemically anchored roof bolts (4 per
strap at 1.2 m centres) Continuous rib strapping retained by 1 m bolts at 1.5
m centres.
The transition to longwall extraction was the
subject of several studies but did not get beyond the feasibility stage.
The
leasehold is dissected by numerous WNW-ESE trending dykes, (approximately 6 per
square km), a large area of the Tongarra seam cindered and the Wongawilli seam
has been intruded by major silling (one borehole indicating > 20 metres thick),
all contributing to difficulties in mine development layout.
Indicated recoverable reserves (>2.0m section)
remaining in the Wongawilli and Tongarra seams upon closure was in excess of 70
million tonnes.
Mine Managers have included:-
M. N. Nielsen Oct. 1951 Jan. 1961
Daniel Hanrahan Jan.1961 Apr. 1964
Harold Sharp Apr. 1964 Apr. 1965
Roger Marshall Apr. 1965 Apr. 1968
Don Eager Apr. 1968 Aug. 1980
Rod Burston (Dep. Man. Nov. 1979); Mine
Manager Aug. 1980 closure.
Typical Coal Specifications 1989
Washery Feed
(Wongawilli/Tongarra coal ratio 65/35%)
|
|
Wongawilli seam coal |
Tongarra seam coal |
|
Ash% (a.d.) |
33 |
30 |
|
V.M.% (a.d.) |
22 |
21 |
|
Spec. En. (Mj/kg) |
22 |
25 |
|
S (total)% |
0.4 |
0.5 |
|
M (inherent)% |
0.9 |
0.8 |
Washery Product
|
|
Fuel coal to Power Station |
Coking coal |
|
Ash% (a.d.) |
28 |
11 |
|
V.M.% (a.d.) |
21 |
28 |
|
Spec. En. (Mj/kg) |
25 |
32 |
|
M (total)% (a.s.) |
5 |
10 |
|
H.G.I. |
64 |
76 |
|
Sizing |
38 x 0.5 mm |
16 x 0 mm |
|
CSN |
3 |
|
|
Ash Fusion (deg C) |
1460 |
|
|
F.C% |
|
60 |
|
Gray King |
|
G10 |
|
Max. Fluidity (ddm) |
|
>14,000 |
|
Max. Mean Reflect. |
|
1.1 |
|